00:00

QUESTION 6

- (Exam Topic 1)
A project’s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)

Correct Answer: BE
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133 https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+soon

QUESTION 7

- (Exam Topic 2)
Which of the following represents the order of the team development stages?

Correct Answer: A

QUESTION 8

- (Exam Topic 1)
A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

Correct Answer: A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156

QUESTION 9

- (Exam Topic 2)
Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?

Correct Answer: D

QUESTION 10

- (Exam Topic 3)
A project is moving into the next phase, and those involved with planning will not actually perform the work. After the project team members have been identified and assigned to do the work, which of the following has changed?

Correct Answer: B