Which technique helps to determine the risks that have the most potential impact on a project?
Correct Answer:
D
Analyzing the strengths, weaknesses, opportunities, and threats (SWOT) of a project is known as:
Correct Answer:
D
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
Correct Answer:
D
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
Correct Answer:
D
You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?
Correct Answer:
A