00:00

QUESTION 101

Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

Correct Answer: C

QUESTION 102

A given schedule activity is most likely to last four weeks. In a best-case scenario, the
schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

Correct Answer: C

QUESTION 103

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

Correct Answer: A

QUESTION 104

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Correct Answer: B

QUESTION 105

What are the key components of the communication model?

Correct Answer: A