QUESTION 111

What quality control tool graphically represents how various elements of a system interrelate?

Correct Answer: B

QUESTION 112

Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

Correct Answer: C

QUESTION 113

An input used in developing the communications management plan is:

Correct Answer: B

QUESTION 114

Which of the following includes how requirements activities will be planned, tracked, and reported?

Correct Answer: C

QUESTION 115

The following is a network diagram for a project.
What is the critical path for the project?

Correct Answer: C