00:00

QUESTION 51

Rex is the project manager of the BDF Project. This project will last for two years and has a budget of $2,345,000. Management has instructed Rex that the project must not go over budget as funds are very tight in the organization. During the project planning Rex and the project team discover a positive risk event to save $75,000. Rex wants to make certain that this risk event happens so which risk response method is most appropriate?

Correct Answer: C

QUESTION 52

You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're
your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

Correct Answer: C

QUESTION 53

You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the project's cost management plan. Why is it necessary to include the project's cost management plan in the preparation for the quantitative risk analysis process?

Correct Answer: C

QUESTION 54

You are working with Anna on your project to determine and map the probability distributions of risk within the project. You have indicated that you will use the uniform
distribution method for a portion of the project. Which part of your project is most likely to have a uniform risk distribution?

Correct Answer: C

QUESTION 55

You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?

Correct Answer: C