When is a Product Backlog item considered complete? (choose the best answer)
Correct Answer:
D
A Product Backlog item is considered complete when it meets the Definition of Done, as stated in [5]: “When a Product Backlog item or an Increment is described as “Done”, everyone must understand what “Done” means. Although this varies significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the definition of “Done” for the Scrum Team and is used to assess when work is complete on the product Increment.”
Why is the Daily Scrum held at the same time and same place?
Correct Answer:
A
According to the Scrum Guide, the Daily Scrum is held at the same time and same place to reduce complexity and promote consistency. The other options are not valid reasons for holding the Daily Scrum at the same time and same place, as they are either irrelevant (such as naming the place) or incorrect (such as being demanded by the Product Owner or booking rooms in advance).