QUESTION 126

There was a change in your portfolio to speed up things resulting in the addition of new components. In order to update the new vision, dependencies and timeline for the components, you should update which of the following?

Correct Answer: A

QUESTION 127

While defining the portfolio, the portfolio manager uses a set of evaluation criteria in order to generate a list of portfolio components for optimization and balancing. Which of the following is not an evaluation criteria?

Correct Answer: D

QUESTION 128

You are currently using a Comparative Advantage Analysis and conducting a what-if analysis to consider how the portfolio component and its intended benefits could be achieved by various options, including resource capability and capacity mix. In which process are you currently working?