QUESTION 46

- (Exam Topic 1)
Which of the following describes a burn rate?

Correct Answer: C
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232

QUESTION 47

- (Exam Topic 3)
A project manager is working on a large, complex project. While creating the project schedule, the project manager defines key points at which progress to date can be identified. Which of the following BEST describes the scheduling activity the project manager has completed?

Correct Answer: B

QUESTION 48

- (Exam Topic 3)
A project sponsor decides to cut the project budget and reduce the scope. As a mitigation plan, the team decides to promote the project internally to gain support from other areas.
Which of the following describes the BEST combination of communication methods that can be used to attract more people?

Correct Answer: A

QUESTION 49

- (Exam Topic 3)
A sprint retrospective is being conducted. Which of the following is the BEST way to obtain input?

Correct Answer: B

QUESTION 50

- (Exam Topic 3)
During a project, the purpose of examining the cost baseline is to:

Correct Answer: C