00:00

QUESTION 16

- (Exam Topic 3)
A project manager chose an architect based on the architect’s presentation, but company policy states vendors must be selected based on the lowest bid. Which of the following applies to this situation?

Correct Answer: D

QUESTION 17

- (Exam Topic 1)
A project team has determined it will need to source data from a system that was not part of the project scope. The role of the project manager is to analyze which of the following impacts?

Correct Answer: C

QUESTION 18

- (Exam Topic 2)
A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?

Correct Answer: B

QUESTION 19

- (Exam Topic 1)
A project manager is justifying a required change with the associated impact on the project. Which of the following is the NEXT step?

Correct Answer: B
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294

QUESTION 20

- (Exam Topic 3)
A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?

Correct Answer: B