- (Exam Topic 3)
A project manager has been receiving conflicting feedback from a variety of team members about the deliverables of another team member. The project manager sets up a mandatory team meeting to discuss the issue. Which of the following BEST describes this approach?
Correct Answer:
D
Reference:
https://www.dummies.com/article/academics-the-arts/study-skills-test-prep/pmp-certification/pmp-certification
- (Exam Topic 3)
A project manager wants to determine the percentage of a project's budgeted costs versus expenditures. Which of the following calculations should the project manager perform?
Correct Answer:
A
Expenditure tracking includes measuring the project spending to date, determining the burn rate (or how fast you’re going through the money), and tracking expenditures to the cost baseline so that stakeholders can see what was planned versus what was actually spent on the project.
- (Exam Topic 1)
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
Correct Answer:
A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
- (Exam Topic 3)
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.
Which of the following is the NEXT appropriate step for the project manager to take?
Correct Answer:
A
- (Exam Topic 3)
A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?
Correct Answer:
B