QUESTION 36

- (Exam Topic 1)
The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?

Correct Answer: C

QUESTION 37

- (Exam Topic 2)
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?

Correct Answer: B

QUESTION 38

- (Exam Topic 2)
Which of the following documents is typically signed by the vendor and includes a reference for how customers’ internal information will be protected?

Correct Answer: D

QUESTION 39

- (Exam Topic 3)
Which of the following documents focus primarily on support activities after the completion of a project? (Choose two.)

Correct Answer: AB

QUESTION 40

- (Exam Topic 1)
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.
PK0-004 dumps exhibit
Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Correct Answer: D