- (Exam Topic 1)
A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
Correct Answer:
A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 292
- (Exam Topic 3)
A vendor notifies the project manager that the scheduled date for a deliverable on the critical path cannot be met due to a lack of resources. Which of the following are MOST likely to be triggered? (Choose three.)
Correct Answer:
ADG
- (Exam Topic 1)
A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?
Correct Answer:
D
- (Exam Topic 3)
A vendor who is scheduled to arrive in two days encounters a delay and needs to reschedule the visit. The project manager needs a timely response from the project sponsor regarding the delay; however, the sponsor is in an all-day meeting and is not responding to email.
Which of the following is the BEST method to get the sponsor’s attention?
Correct Answer:
C
- (Exam Topic 2)
Which of the following project phases would MOST likely include a creating transition plan?
Correct Answer:
D